Our commitment to clear and safe network planning

Plant Map Purchase and Notification of Commencement of Earthwork

Under the Singapore Telecommunications Act, all contractors must obtain information on the location of telecommunication underground services and secure approval from the respective telecommunication system licensee (telco) before carrying out any earthworks.

For reference, the latest [Earthworks Requirements] is available for download.

Plant Map Purchase

Obtain maps showing the approximate location of underground telecommunication ducts and manholes before starting earthworks.

How to apply:

1

Network infrastructure icon

Complete the [Purchase of Plant Maps] form and attach site plan(s) in PDF, indicating the location(s) of proposed work.

2

Network infrastructure icon

Upload the completed Plant Map form and attachments here.

Note: Each request covers a maximum distance of up to 1 km.

Notification of Commencement of Earthwork (NCE)

Notification to the telco before digging or doing earthworks near underground cables or ducts. It helps to protect the telecom network and prevent accidental damage.

How to apply:

1

Network infrastructure icon

Complete the [NCE form] and attach site plan(s) in PDF, showing proposed trial holes and earthwork positions relative to BlueTel’s plant route.

2

Network infrastructure icon

Attach your project work schedule.

3

Network infrastructure icon

Include Cable Detection Drawing(s) from your TCDW, if applicable.

4

Network infrastructure icon

Upload the completed NCE form and attachments here.

The form for Final Approval application can be downloaded at [Application for Final Approval]

Special Note

For emergency works, please email osp_plantmap@bluetel.net.sg and osp_nce@bluetel.net.sg within 24 hours of commencement, providing:

1. The work location, and
2. Contact details of the site supervisor.